Share 9th Street Stairs on FacebookShare 9th Street Stairs on TwitterShare 9th Street Stairs on LinkedinEmail 9th Street Stairs link
9th Street City Stairs Project
Historically, wooden stairs were constructed in Park City's Old Town right of ways providing walkable pedestrian access. In the 1980s, Park City dedicated an ongoing redevelopment budget to replace and repair the deteriorating stairs and construct new stair sections in the priority order identified through community discussions. During construction, wooden stair treads were upgraded to metal increasing safety and longevity while reducing maintenance costs.
Over time, stairs have been constructed and improved in almost all Old Town's rights-of-way. However, three city blocks on 9th Street and one block on 10th Street remain unbuilt, leaving some residents less walkable access. These remaining blocks are key pedestrian links between Lower Main Street and the Old Town Neighborhoods surrounding them.
Neighborhood discussions are vital to determine the future of 9th Street. We welcome and appreciate your feedback.
A brief history of Old Town stairs
Funding
Late 1980s, the City began a program to replace the dilapidated Old Town Stairs
1982 Main Street Redevelopment created. No longer generating revenue.
1990 Lower Park Avenue RDA created – 2015 LPA RDA extended
Old Town Stairs budgeted through Main Street and LPA RDAs in 80s and 90s
Funding must be used within the RDA boundary for budgeted improvements
Main Street RDA – Stairs complete
4 Blocks to complete the LPA Stair projects
Reconstruction Program
Started in late 80s within the Main Street RDA
1995 – two neighborhood meetings/reprioritization by City staff
1997 – Trails and Stairs Inventory
1998 – CIP Budget overhaul – OTS remained a high priority, CIP #0003
Systematically replaced old stairs in rights of way:
Replaced old wooden stairs and concrete walks
Replaced wooden treads with metal treads
Constructed new stairs in unbuilt ROWs
Three blocks on 9th Street and one block on 10th Street are only remaining unbuilt ROWs
Prioritized in the 2015 Old Town Stairs CIP – Lower Park Ave RDA funding
9th Street Planning
The purchase of Treasure Hill reprioritized 6th Street Stairs Woodside to Treasure over 9th Street Stairs. Additionally:
2018/19 Planning application for a driveway in 9th Street ROW for 901 Woodside. The application included a walkway and stairs
Received comments from Planning Commission/Council/Old Town residents to build out the remaining ROWs – specifically 9th Street
Survey, design, and engineering contract for 6th Street included 9th Street survey, design and engineering
June 2021 – 901 Woodside abandoned the driveway in ROW and stairs section
August 2021, 6th Street Stairs construction completed
Late August 2021, 9th Street ROW survey work performed
City received emails from neighbors because of survey crew in the ROW
Austin Taylor– tour with neighbors
November 8, 2021, preliminary survey complete
December 2021, preliminary stairs layout and utility conflicts identified.
Michelle updated neighbors by email
Neighbors responded
January-February 2022, preliminary plans for Park Ave to Woodside. Discussed parking conflicts and intersection improvements
Staff developing a plan to gather neighborhood input
9th Street City Stairs Project
Historically, wooden stairs were constructed in Park City's Old Town right of ways providing walkable pedestrian access. In the 1980s, Park City dedicated an ongoing redevelopment budget to replace and repair the deteriorating stairs and construct new stair sections in the priority order identified through community discussions. During construction, wooden stair treads were upgraded to metal increasing safety and longevity while reducing maintenance costs.
Over time, stairs have been constructed and improved in almost all Old Town's rights-of-way. However, three city blocks on 9th Street and one block on 10th Street remain unbuilt, leaving some residents less walkable access. These remaining blocks are key pedestrian links between Lower Main Street and the Old Town Neighborhoods surrounding them.
Neighborhood discussions are vital to determine the future of 9th Street. We welcome and appreciate your feedback.
A brief history of Old Town stairs
Funding
Late 1980s, the City began a program to replace the dilapidated Old Town Stairs
1982 Main Street Redevelopment created. No longer generating revenue.
1990 Lower Park Avenue RDA created – 2015 LPA RDA extended
Old Town Stairs budgeted through Main Street and LPA RDAs in 80s and 90s
Funding must be used within the RDA boundary for budgeted improvements
Main Street RDA – Stairs complete
4 Blocks to complete the LPA Stair projects
Reconstruction Program
Started in late 80s within the Main Street RDA
1995 – two neighborhood meetings/reprioritization by City staff
1997 – Trails and Stairs Inventory
1998 – CIP Budget overhaul – OTS remained a high priority, CIP #0003
Systematically replaced old stairs in rights of way:
Replaced old wooden stairs and concrete walks
Replaced wooden treads with metal treads
Constructed new stairs in unbuilt ROWs
Three blocks on 9th Street and one block on 10th Street are only remaining unbuilt ROWs
Prioritized in the 2015 Old Town Stairs CIP – Lower Park Ave RDA funding
9th Street Planning
The purchase of Treasure Hill reprioritized 6th Street Stairs Woodside to Treasure over 9th Street Stairs. Additionally:
2018/19 Planning application for a driveway in 9th Street ROW for 901 Woodside. The application included a walkway and stairs
Received comments from Planning Commission/Council/Old Town residents to build out the remaining ROWs – specifically 9th Street
Survey, design, and engineering contract for 6th Street included 9th Street survey, design and engineering
June 2021 – 901 Woodside abandoned the driveway in ROW and stairs section
August 2021, 6th Street Stairs construction completed
Late August 2021, 9th Street ROW survey work performed
City received emails from neighbors because of survey crew in the ROW
Austin Taylor– tour with neighbors
November 8, 2021, preliminary survey complete
December 2021, preliminary stairs layout and utility conflicts identified.
Michelle updated neighbors by email
Neighbors responded
January-February 2022, preliminary plans for Park Ave to Woodside. Discussed parking conflicts and intersection improvements
Staff developing a plan to gather neighborhood input